testata inforMARE
Cerca
14 February 2026 - Year XXX
Independent journal on economy and transport policy
00:55 GMT+1
LinnkedInTwitterFacebook
FORUM of Shipping
and Logistics
The World Bank

MEASURING PORT PERFORMANCE

Patrick Fourgeaud



1 - PREAMBLE

This note proposes a more customized approach of indicators used to monitor port performance, forecast development and set targets in port sector projects. The main points are that, in most cases, it is not possible to determine benchmarks which would be applicable for any port, and that all expressions of port performance do not address the same requirements. Therefore, carefully identifying problems to be monitored and taking into account the main characteristics of the commercial activity should lead to more accurate indicators and targets.

Available data: In public ports, expressions of port performance are based on data recorded by port authorities which traditionally tend to focus on traffic recordings and parameters used in tariffing of port services. Most available and reliable data are related to the maritime interface where information is more easily collected than on the land interface. Port Authorities usually monitor berth occupancy and dwelling time of ships, characteristics of calls, performance of ship-to-shore cargo handling and availability of the main pieces of handling equipment. Additional but often less reliable data may be available as regards landward operations: dwelling time of cargo in ports' warehouses and storage areas, characteristics of Customs and other administrative procedures and, rarely, performance of handling for pick-up and delivery of goods...

Most of the time, developing a relevant set of indicators would require more information; a survey is the only way to identify whether existing data are reliable, the cause and extent of existing problems and the way they could be monitored.

Whatever criteria are chosen, they must be associated with a precise definition of what is recorded, as all port authorities do not take into account all parameters the same way; for example, they may include empty containers, shifted and transshipped boxes or the tare weight of unitized goods.

Forecast: These indicators are often used to forecast port productivity and assess future capacity. Computerized simulation systems can give accurate estimates of berth capacity and ships' waiting time. Various statistical programs designed for all purpose process modeling or specialized in transportation and port logistics may be used. This note will remind of some simplifications of the queuing theory, which can give rough estimates in some simple cases.

Performance and competitiveness: These expressions of performance display mainly a technical capacity. But shippers and ship-owners have additional requirements; they are also looking for:

  • reliability: a steady and predictable performance adapted to shipping lines schedules;

  • cost: a high performance at a competitive and predictable cost;

  • quality: no overage, no wastage or pilferage or any damage registered during handling and storage ope-rations. Progressively, producers and transporters have to comply with international standards (ISO 9000 or equivalent) and get their process certified; ports, at least those operating in a competitive environment, have to catch up with this trend;

  • adaptability: a capacity to listen to their problems and needs, negotiate and propose solutions.

A port is also a link in the transport chain and, of course, similar requirements apply as regards capacity, performance and quality of connections with short-sea and feeder shipping lines, and with inland transportation networks : road, rail, barges.

Complying with these requirements results is competitiveness and, ultimately, growing market share; ports process more traffic and shippers benefit from lower freight rates and insurance premiums. This can be assessed mainly indirectly. Fortunately, performance and competitiveness are more or less linked: high productivity is often synonymous with reliability and quality and, not systematically, with low costs. Therefore, performance and cost targets are an acceptable approximation of competitiveness.

1.2- technical valuation of port performance

Port operations are increasingly specialized and processed in dedicated terminals but many flows of goods are still handled at general purpose berths. Depending on the case, port performance should be assessed for an homogenous set of berths or a terminal. It is usually expressed as the average number of calls and the average flow-volume or weight-of goods over a standard period of time; number of calls per berth and per year, volume or weight of cargo handled per hour, per call or per day, per gang or per crane.

In addition, other criteria can be used to see how existing capacity and performance meet the requirements of: i) the shipper or the ship-owner: mainly average waiting time of ship, dwelling time of cargo and data related to quality if possible, and: ii) of the Port Authority: basically berth occupancy rate and global traffic.

All these parameters are not equivalent:

  • "snap-shot"performance (recorded during an hour, a shift, a call) describes the technical capacity of a terminal; a flow of goods recorded within a larger period depends also on parameters related to competitiveness, market share, seasonal effects, berthing capacity etc.

  • Some of them are used to monitor specific points of concern for port authorities, operators or clients and cannot improve simultaneously. For example, Port Authorities are looking for relatively high berth occupancy rates whereas shippers do not accept significant waiting time.

1.3- explanatory factors

High performance is observed in private terminals and poorest performance is often associated with ports run by public Port Authorities, still in charge of cargo handling and maintenance of equipment. Beyond such a statement, explaining a poor or a good performance may require a more thorough analysis.

Exceptionally high performances occur when all parameters concur positively: as far as containers are concerned, the typical high-performing terminal is dedicated to one or a few shipping lines and privately run, processes regular and well timed calls of large ships, with economies of scale allowing it to be geared with the most high-performing gantry cranes, and handles shipments representing the major part of the ship capacity. Similar parameters can be mentioned in the case of bulk (freighted) traffic.

Conversely, in poor performing ports, many causes, often interrelated, may be mentioned,:

  • Physical characteristics, mainly: nautical access: dredging backlog and other factors narrowing the access time-slot; land access: ill-maintained pavements, restricted access to land-transportation networks; and port capacity: lack of berths and storage areas, insufficient room for modern ship to shore operations;

  • Organizational parameters, related to ships: old ships with narrow hatches, large tween decks, slow moving derricks, spending too long idle time at berth; cargo: ill packaged, non unitized, damaged goods, organization of lashing-unlashing of containers; handling capacity: unsuitable and ill-maintained handling equipment, poorly trained work force, not enough crane drivers, unsuitable, congested and poorly managed storage areas; organization: non-productive methods, ill prepared calls, too restricted working-time, unwillingness of port operators to work at night, commercial operations interfering with ship-to-shore operations, excessive dwelling time of cargo for commercial motives, documentation delays; procedures: lengthy customs and other administrative procedures and controls, corruption.

Public port authorities but also other administrations, port operators, ship-owners, and shippers, involved in this process with their own objectives, may be partly responsible for these shortcomings. A rapid survey of the situation should help identify the main causes of the problems and choose adapted criteria to monitor further progress.

1.4- measuring port performances - basics

Poor performances are generally due to the organization of handling and storage operations and of maintenance. Therefore, the most common and practical way to measure port performance is to check whether organization and yard equipment can match the actual capacity of the main hoisting machines: generally quay cranes or gantries, which are the most expensive and high-performing pieces of equipment.

The first step consists in determining the nominal and the optimum-or commercial-output:

  • The nominal output of a crane or a gantry is the theoretical result when all parameters are optimized and reliability is absolute; it can be precisely assessed by taking into account :

    . the average load to be handled:

    .. break-bulk and unitized traffic: unit load plus accessories: spreaders... ;

    .. dry bulk traffic : weight of buckets plus capacity x density of product,

  • the average duration of a whole handling cycle (loading or unloading), taking into account the length and speed of each elementary move: hoist, translation, rotation, lowering and back to hold, with and without the load, according to the manufacturer's technical specifications;

  • The commercial output is lower; due to various factors:

    . physical factors such as nautical and weather conditions impairing average performance: tide, swell, wind or rain;

    . factors related to port operations: average ships' characteristics, time spent in stowage, trimming, for opening or closing of hatch-covers, lashing-unlashing of containers, etc.

    . equipment related factors: standard reliability of cranes, the time it takes to shift them, to change buckets or spreaders, and organization of work, i.e.: proportion of effective work-time during a shift;

The second step is to identify the main causes of poor performance and choosing adapted and measurable criteria.

Over a long period of time, additional delays must be deduced from the commercial output to take into account the extra time spent by ships when they are berthed, before and after commercial operations, waiting for various motives: due to nautical and weather constraints, because of locks or swaying bridges, waiting for port services (bunkerage, repairs), because of non flexible working time.

Benchmark: Most container gantry cranes have a theoretical output of 35 to 40 moves per hour or more. The commercial output, depending on local conditions, varies usually from 15 to 35 in average, with peak performance nearing theoretical performance.

The Delta Sea-Land Terminal at Rotterdam has recently invested in double-trolley gantry cranes and a fully integrated and automatized system between ships and stacking areas which is intended to reach 50 TEUs per hour and per hold, i.e., almost doubling the usual output.

In the case of continuous handling of bulk products, the commercial performance may be closer to the theoretical output (80 to 90 %) with peak performance exceeding theoretical performance, depending on the reliability of equipment and the characteristics and number of products to be handled during a call.

As far as the performance of the land interface is concerned, the problem is generally the lack of data;

  • Average cargo dwelling time. A distinction should be drawn between the impact of customs and other administrative procedures, of shortcomings in storage management and cargo handling, and of commercial practices (e.g., when port storage is less expensive than private warehousing). The average dwelling time should not exceed 5 days for containers, 7 to 10 days for general cargo, two weeks for bulk products. Commercial constraints may lead to longer delays.

  • the average time spent by a trailer waiting for its load to be located, handled, and to get its clearance, is usually known only through occasional surveys, even though pick-up and delivery of goods often accounts for a large part of the port congestion and inefficiency. It should not exceed 4 to 6 hours. 2 hours are the norm in modern container terminals.

Regarding equipment reliability, two parameters must be identified: i) the reliability in operation, i.e., the number and length of breakdowns occurring during commercial operations and: ii) the average availa-bility, after deduction of planned maintenance and all breakdowns.

For small pieces of equipment like tractors, trailers, forklifts, availability should be very high (95 % or higher), provided that their number matches the demand and standard preventive maintenance is performed.

Regarding gantries, cranes, RTGs, breakdowns may occur and stop port operations; with normal preventive maintenance, most of them should be limited to electricity and automation problems and repaired within a few hours. Availability should be more than 90 %. The norm in modern terminals is close to 98 %, or 2% unscheduled downtime.

An occasional lack of gantry-cranes drivers may reduce the above availability ; this parameter is not always identified.


2 - APPLICATION

2.1 - containers

Container terminals performance depends on:

  • ratio loaded vs. unloaded containers: empty boxes are not always included in the port statistics (they may be considered as other tare weights) but have to be handled;

  • unproductive moves, i.e., the handling of all the containers that do not have to be unloaded but have to be moved: mostly empty and light containers and those containing hazardous materials, loaded on top or on the deck;

  • the level of automation of the gantry-cranes; one of the limiting phases of the handling cycle is the time spent positioning accurately the spreader on a container (loading), or the container on a trailer, a MAFI trailer (specialized equipment used to shift containers within port limits) or a chassis maneuvering on the apron (unloading).

Most modern gantries are automated and equipped with anti-sway devices, and now, the problem is more the capacity to deliver or remove containers without delaying ship-to-shore operations.

  • the average weight of containers and the proportion of containers requiring special attention: flats, liquid bulks, reefers etc.; and the mix of containers of various sizes: 20'/40'/45' which will require to maneuver or change spreaders;

  • commercial constraints; most of the lines calling at a port may have similar commercial constraints, leading to unevenly distributed calls.

Highest performance is observed during calls of large container-carriers loading and unloading a large number of containers, with balanced flows of full containers in and out; terminals dedicated to a single company can be highly productive (mainly East-West traffic);

Various analytical approaches have been proposed; in 1998, Drewry proposed linear functions of the vessel size and of the proportion of the ship's capacity to be handled during one call.

(source: Drewry Shipping consultants: World Container Terminals 1997).



As far as costs are concerned, and since containerization is a completely standardized process, it is widely accepted that there is a single benchmark for all terminals operating a main flow of containers in optimum conditions: about US$100 for all handling and storage costs from ship to gate. Practically, real costs may vary from US$ 80-90 in some terminals to more than US$ 400.

the case study below compares two different situations in order to demonstrate how different parameters may affect performances.

Case no. 1: ship size: 3rd generation and larger, length: about 300 m, calling for 1,000 containers or 1,500 TEUs, average load per TEU:10 ton, proportion of 40-foot containers: 50 %, proportion of empty containers: 10 %, 2 to 3 gantries per ship (3 gangs),

In that case, the capacity of the gantry cranes can be fully exploited: the commercial output can be 25 to 30 move / hour / crane in average.

According to the above assumptions, performances can be expressed as follows:

TEU f = TEU full
TEU e = TEU empty

ratios : 37.5 to 45 TEU f+e /hour/gantry, 34 to 40 TEU f /hour/gantry
94 to 135 TEU f+e /hour, 85 to 120 TEU f /hour, 850 to 1,200 ton/hour,
2 to 3 shifts are required
1 call / 2 days, 180 calls, 180,000 cts 2 calls / 3 days, 240 calls, 240,000 cts
240,000 TEU f /year1, 320,000 TEU f /year
2,400,000 ton/year, 3,200,000 ton/year
8,000 ton/year per meter of berth 10,600 ton/year/meter of berth

This computation presupposes that several berths are available; a one berth configuration would not be flexible enough and could not perform efficiently; as soon as ships are moored, stevedoring operations are supposed to start; they sail off at the end of commercial operations without delay.

Ratios higher than 10,000 ton/year per meter of quay length may be obtained: i) when large container carriers are fully loaded or unloaded; ii) if traffic and port organization allow to raise the berth occupancy rate without congestion; for example, with 6 calls per week, i.e., 300 calls per year, the ratio becomes: 13,250 ton/year/meter of berth.

Conversely, lower performances are recorded when smaller container-carriers call for a limited number of containers and have to handle many empty boxes (mainly North-South traffic);

case no. 2: ship size: 1st and 2nd generation, length: less than 250 m, calling for 700 TEUs or 500 containers, average load per TEU: 13 ton, proportion of 40-foot containers: 40 %, proportion of empty containers: 30 %, 1 to 2 cranes and 1 or 2 ship derricks (3 gangs) per call, 2 calls every 3 days;

Performance: 20 to 25 move/hour with gantry-crane, 12 to 15 move/hour with cranes or derricks,

With this new set of assumptions, the former expressions of performance are modified as follows:

ratios : 28 to 35 TEU f+e /hour/gantry, 17 to 21 TEU f+e /hour/ crane or derrick,
62 to 91 TEU f+e /hour,
20 to 25 TEU f /hour/gantry, 12 to 15 TEU f /hour/ crane or derrick,
44 to 65 TEU f /hour/,
572 to 845 ton/hour,
2 shifts are required
120,000 TEU/year per berth, (1 cf previous case)
1,550,000 ton/year, 6,200 ton/year per meter of berth length.

This last result must be compared with 10,000 ton/m in case no.1; both examples correspond to different but well operated terminals.

2.2- break-bulk :

Due to the wide range of products, ships, equipment, methods..., assuming an average performance for all kinds of commodities and packaging makes little sense:

  • Specialized traffic like paper, frozen meat, fish or fruits should be studied separately, according to their packaging and to the type of ship and handling equipment (specialized or not); see appendix one, the case of fruit handling.

  • Most commodities in big bags, pre-slung or pre-palletized loads, pallets, nets etc., can be handled with a crane; a good organization should adapt to a rhythm of one cycle every 1.5 to 3 minutes (20 to 40 moves per hour), depending on the nature of the cargo, the unit weight of the load, the ship's size and other factors as weather conditions, tide and swell, etc. Whenever the volume of goods to be handled is large enough to allow for a reasonable cost recovery of additional equipment, special devices can be adapted to improve the unit load or to shorten the cycle.

examples:

cements bags : 2 ton pallets built in the hold or on the apron: 40 ton/hour/crane. Pre-palletized bags: 80 ton/hour/crane, and more with spreaders. Cement in bulk can be handled at much higher speed.

exotic wood: logs up to 6-8 tons, handled by the piece with hydraulic clamps: 120 to 160 ton/hour/crane. Logs handled with slings; less than 100 ton/hour; only in daylight.

2.3- dry bulk traffic

agri-food products / fertilizers :

These low-density products are transported in bulk-carriers ranging from small cargo-boats (5,000 dwt) to cape-size bulk-carriers used for basic products (100 to 130,000 dwt ships).

Handling of export products is operated mainly with conveyors, whenever possible, with performances varying from 100 to nearly 1,000 ton/hour per conveyor, depending on ship size, port equipment, product characteristics and density, brittleness, and environmental and safety considerations linked to dust.

Ship to shore operations of import products require cranes and hoppers (20 to 35 ton capacity - 150 to 300 ton/hour), or elevators (400 to 1000 ton/hour) : two to three cranes per ship, or one elevator and two or more cranes on panamax and larger ships;

On the apron, small cargoes are generally loaded in trailers; large cargoes are carried through conveyor belts to warehouses or silos. High performance may be reached only if ship to shore operations are dissociated from commercial operations. Direct delivery alongside is the major cause of poor performance in bulk handling.

ratios : small bulk-carrier, 1500 to 3000 t shipment: 100/120 ton/hour per crane : 2 cranes
operated in one day
from panamax up to cape-size, 60,000 t shipment: 1 elevator and 2 cranes :
1,100 ton/hour, 15 to 18,000 ton/day
operated in four days

That performance may be reduced when operating multi-product cargo-ships. Some sticky, dusty or hard-to-handle products, such as manioc roots, impair the average performance. Brittle or dusty products may require lower handling rate for quality, safety and environmental purposes.

ore - coal : Export cargoes are usually loaded with conveyors; 1,000 to 2,000 ton/hour or more. Import traffic is handled with large gantry cranes geared with very large grabs: up to 1,000 ton/hour/gantry crane or with special devices. Same constraints, related to quality, safety and environment, may have to be taken into consideration.

Bulk-carriers ranging from the panamax to the cape-size: throughput: up to 15 to 20,000 ton/day

2.4- liquid bulk traffic

Generally, unloading performances depend on the size of the ship which provides pumps and energy. They depend also on its viscosity, temperature, and on safety regulations, for hazardous products. Most liquid carriers are operated within one day, whatever the size.

throughput : 300 to 1,000 cu m /hour, up to 10,000 cu m /hour and more for very large tankers.


3 - THE LABOR ISSUE

The staffing issue is one of the most complex and its successful settlement is often a key factor in a port restructuring process. Some indications are summarized thereafter

3.1- principles

Globally, transportation systems are increasingly productive, automatized and capital intensive. In all segments of the transport chain, direct employment tends to be reduced and more qualified. As far as ports are concerned, the situation where old public organizations integrated many or all port-related functions, which ended usually in a too large and poorly managed workforce, limited or poor level of services and high operating costs, is changing. Now, the private sector is increasingly associated in more efficient and competitive port operations, mainly through concessioning of infrastructures and privatization of services. The result is reduced staffing at all levels, higher qualification requirements and improved human resources management. Conversely, better performing ports contribute to foster trade and develop national economies.


Whenever possible, first addressing the overstaffing issue will facilitate the involvement of the private sector . Since this situation is often the result of governmental policies considering port organizations as natural shelters for an unemployed and unskilled workforce, the same authorities have definitively a responsibility in helping dismantle the system and make sure that the consequences are properly cushioned. This supposes that adequate budgetary means and staff management skills are made available early enough in the process.

The concessioning process generally starts with industrial bulk and container terminals, because these activities are easily standardized and can be operated efficiently and with profit. Other fields of the port activity have often more severe problems and excessive staffing levels:

  • The remaining port activities depend more on local conditions; they are subject to variations, due to seasonal effects, meteorology, variation in packaging and handling methods, low frequency of some operations etc.;

  • with less economies of scale, operators of non unitized general cargo and miscellaneous bulks cannot easily invest in modern equipment and methods and these activities are less often reorganized;

  • the status of dock-workers placed under the responsibility of public authorities and hired intermittently by stevedores, once justified because of abusive practices, is still maintained in some countries; but, this organization, created to protect an undifferentiated low-skilled work-force in a context of weak labor regulations cannot evolve and does not correspond any longer to modern trends.

  • In addition, some ports still maintain skilled workers and large workshops in order to undertake most or all of maintenance work; same thing as regards dredging;

  • specific factors as social commitments of port authorities (health centers, housing etc.), inappropriate monitoring and tariffing procedures based on customs-like tax scales, are an additional cause of excessive administrative staffing.

The overstaffing issue is not easily addressed. Worldwide experience leads to recommend that the trade unions be brought to the negotiations table from the outset, when the reform program starts being devised. Actually, the most valid way to build confidence in the process while incorporating in it lessons of experience and market-oriented concerns is to bring together port users, port labor and port and maritime employers. The objective is to allow all stakeholders to share common concerns about competitiveness of port services, and a better understanding of how any weakening of this competitiveness would be detrimental to all, and in particular to the workforce which would be the first to bear the consequences of reduced economic activity, both inside and outside the port

3.2- proposed benchmarks

Port Authorities:

Some tentative benchmarks are proposed for Landlord Ports regulating a diversified activity, managing a proportionate public and private domain and not implied in commercial operations or services to ships such as pilotage or towage.

Size of the Port Authority     recommended staffing level
small authority: a few millions tons: about 50
average port authority: 10 to 20 M tons: from 150 to 200
large ports: example: R'dam: 300 M tons: 1,100
More generally, an indicative ratio would be: 100,000 ton per staff per year, with large variations:
  • small ports require more than this proportion, large ports are more productive;
  • general cargo requires more staffing than bulk traffic.

Port operations

Containers: The recent study by Drewry, cited supra, as well as other comparisons between efficiently run container terminals, show a relatively constant productivity of about 1000 TEUs per staff per year, for a large array of yearly throughput, from 150,000 up to 600,000 TEUs. This includes all staff: operational, administrative and management.

Bulks: these operations require very few people: most automatized processes include large gantries and belt conveyors, that require only skilled drivers, a few supervisors and adapted crews for instant maintenance in hydraulics, electricity and automation. Additional staff are required occasionally, at the beginning, for preparation, and at the end, for trimming of remaining cargo, and for the cleaning of equipment.

Other operations (small bulks and general cargo):

In most cases, licensed port operators have a diversified activity: handling of various commodities, shipping agency, freight forwarding, inland storage etc., that helps them balance the level of employment. Usually, they try to limit the level of unemployment, specially when the old system of guaranteed salary for dock-workers has been rescinded, but they cannot face peak periods. That may occasionally lead to operate undermanned ships, hire temporary workers for low skilled positions, differ storage operations etc.

An average productiveness can be computed only as regards cargo handling (ship to shore), for a given commodity and handling technique. Some examples below show the large variation in productiveness.

Examples:

1) boxes in 2-ton pallets built in the hold (fruits, frozen goods etc.):
gang: total, 15 to 17 dockers, not incl.: transfer and storage crew, crane driver, maintenance staff;
productiveness: 50 ton per hour 3 ton /h / docker
 
2) pre-palletized boxes, handled with cages:
gang: about 13, including transfer, not incl.: storage crew / crane driver / maintenance staff;
productiveness: 225 ton per hour 17 ton / h / docker
 
 
3) exotic wood in logs, handled with slings:
gang: 12 to 15 dockers, not incl.: transfer and storage crew / crane driver / maintenance staff;
productiveness: 80 ton per hour 6 ton / h / docker
 
 
4) exotic wood in logs, handled with hydraulic clamps:
gang: 10 dockers, not incl.: transfer and storage crew / crane driver / maintenance staff;
productiveness: 140 ton per hour 14 ton / h / docker


Economic approach

Some modern ports have computed the global workforce related to the port activity, including handling operations, ship services and administration of both authorities and private sector: these figures relate to the port communities and are used in economic studies.

Some examples:

Rotterdam (1997): 300 M tons about 25,000 jobs
All (25) French Ports (1995): 275 M tons about 35,000 jobs



4- NOTE ON BERTH OCCUPANCY RATE AND QUEUING THEORY:

Ships are berthed according to available space and other constraints as number and size of bollards, number and location of main pieces of handling equipment, nautical constraints etc. For example, a 1000-meter quay can theoretically receive three large Panamax-type ships or four or five smaller ones. Only simulation systems could take these details into account. Analytical approaches require that a number of berths be specified in advance. It must be done by considering the length of ships commonly operated. Thus, if a terminal actually accommodates ships with various sizes and berthing space can be optimized, its real capacity may be slightly underestimated when using the methods described below.

4.1- berth occupancy rate

This rate is usually computed over a year, to include seasonal effects:

Cargo handling performance may be monitored by recording:

cumulated length of commercial operations alongside the quay v/s...
...available time over the given period

The optimal use of infrastructure might be best monitored with the following ratio:

cumulated length of call alongside the quay (including idle time) v/s...
...available time over the given period (365 x 24 h)

The difference accounts for all tasks and procedures to be performed when the ship is berthed, at the beginning or the end of the call. It also includes the consequences of the organization of work: restricted working time, lack of flexibility (shifts scheduled at fixed hours) etc., and the consequences of other constraints that apply to ships mooring or sailing out (tide, current, availability of pilots and tugs, swing bridges, locks...).

A distinction must be made according to the way ships are chartered:

Liner-ships have to comply with a precise schedule. If no berth is available at the time of arrival, the call may be canceled, the cargo shifted to another port or waiting for the next call. Thus, whenever competition exists between ports, the berth occupancy rate usually does not exceed 50 to 60 %. Higher rates can be seen when port facilities are saturated and there is no alternative, or when it is possible to schedule precisely a high number of calls; e.g., terminals dedicated to a single intensive traffic like short-sea Ro/Ro traffic or some private terminals operating on East-West trade with very intensive and well coordinated activity.

chartered ships are usually less affected by port congestion, depending on the nature of the cargo, the demurrage rate. Calls may be planned only a few days or weeks in advance. Their length may vary according to the nature and the size of the shipment. High berth occupancy rates can be observed, up to 80 %, sometimes more, generating significant waiting time.

Expanding the working period to 3 shifts per day and to the week-end, whenever possible, is the first and simplest way of improving this ratio.

4.2- queuing theories and simulations

Port congestion can be precisely assessed by using simulation models taking into account each significant step of the process. In some case, rough estimates can be obtained through simplifying methods. A common one is based on the computation of the ratio: waiting time/operating time, according to the berth occupancy rate and the number of berths .

Theoretical requirements are: a set of identical berths where an homogenous fleet of ships call on a first come first save basis. Arrival patterns and distributions of service times are approximated by a statistical law (Erlang distribution), simulating processes ranging from the random distribution (Erlang 1) to increasingly regular ones (Erlang 2, 3...).

The average assumptions for a freighted traffic are:

  • no distinctive pattern of calls  -»  arrival at random,

  • and various types of cargoes  -»  service time at random.

  • or homogeneous traffic  -»  more regular service time, increasing order of the Erlang law1,

The average assumptions for liner traffic are:

  • strict compliance with a schedule, i.e., a fixed distribution pattern of arrivals,  -»  (Erlang §), practically Erlang law at 2 to 4th order.

  • variation of service time depending on the nature and size of shipment.  -»  increasing order.

This method is more suitable for chartered traffic and should not be applied to liner ships, as long as they do not wait. In such a case , the max berth occupancy rate depends primarily on the actual possibility to schedule calls evenly distributed.

This method represents correctly two phenomena:

  • a very rapidly increasing waiting time when the berth occupancy rate rises;

  • a very rapidly decreasing waiting time when the number of berths increases; dedicating an additional berth to an existing traffic improves flexibility and capacity to a much larger extent than the mere relative increase in the number of berths.

Generally, the maximum berth occupancy rate (corresponding to a low average waiting time) is lower with liners than with freighters.

nota:The Erlang function is implicit. It has been tabulated for some current cases or graphically translated. See in appendix 2 the table for E2/E2/N traffic (arrival and service time distributed according to an Erlang 2 law) and some graphs corresponding to usual combinations when arrivals are at random. The graphs give: waiting time v/s service time, according to the berth occupancy rate and the number of berths.





synthesis of the proposed approaches;

mode
commodity
handling method
shipment's size
output per call
 
unitizedcontainersEast-West traffic
Gantry cranes
1,500 TEUs / call85 to 120 TEUs/hour11,000 ton/year/ meter of quay length
 containersNorth-South traffic
gantries and derricks
700 TEUs / call60 to 90 TEUs/h6,000 ton/year/ meter of quay length
break-bulkcement:in/out2 ton palletsvariable120 to 240 ton/h 
 logs: unload.hydraulic clamps3 to 5,000 ton300 to 400 ton/h 
 logs: unload:slings3 to 5,000 ton< 300 ton/h daylight only
 fruitsbox on palletsvariable42 to 55 ton/h 
 " " "Pre-palletizedvariable225 ton/h 
unitiz. containerizedvariable700 ton/h 
dry bulkanimal feedst.elevators30 to 60,000 ton1,100 ton/h 
 " " " " " "cranes5,000 ton300 ton/h 
 ore/coalcranesvariable large1,000 to 1,500 ton/h 
liquid bulkcrude oilpumpslarge (VLCC)up to 15,000 ton/h 
 misc.pumpsvariable, small300 to 1,000 ton/h 


Berth occupancy rateLiner shipping40 to 60 %No delay; competitive traffic
 Freighted traffic60 %, up to 80 %Significant delays


Port equipment availabilityTractor - trailers90 - 95 %adapted fleet - adapted maintenance
 Gantries - cranes80 - 90 %adapted maintenance




Appendix n. 1: handling of boxes

Bananas, and other fruits, are packed in cardboard boxes, whose size and weight differ according to the final destination (roughly: 0.40 x 0.50 m; variable height ; 13,5 to 19.5 kg).

Three ways of handling these boxes are listed below, according to the resulting output:

i) boxes are handled in bulk; ships are loaded by building pallets on the apron and dismantling them in the hold (the cargo can be unloaded the same way). This is the traditional (and slow) way of handling boxes and bags, requiring a large work-force. On the other hand, the full capacity of reefers can be used (less broken stowage in old ships).

In average, a good handling throughput is about:

15 to 20 pallet/hour per hold,
i.e.: 720 to 960 box/hour,
or, with 19.5 kg boxes (48 boxes per pallet), about: 14 to 19 ton/hour;
on three holds, an expected throughput can be: 2,100 to 2,800 box/hour
or: 42 to 55 ton/hour.
With 20 working hours per day: 850 to 1,100 ton/day
or, with the same assumptions: 42 to 56,000 box/day

ii) pre-palletization is more and more widespread. Palletized fruits may be handled with cages holding two to four pallets at a time (when there is no more space in the hold to operate this way, each loading level is ended with several pre-slung pallets); cages are loaded/unloaded on the apron by one or two twin-fork front loaders, holding 2 pallets at a time; they are handled in the hold by four dock-workers using pallet-trucks. The average output, strongly depending upon organization of space and of operations, can be very high; at peak production, up to 150 pallet/hour per hold,

in average:

80 / 100 pallet/hour per hold,
with 80 pallets/hour/hold in average: 3,800 box/hour per hold
or: 75 ton/hour per hold,
on three holds: 11,400 boxes/hour
or: 225 ton/hour,
with 20 working hours/day: 4,500 ton/day;
or: 230,000 box/day,

iii) containerization: this is the last step of unitization; it is much more capital-intensive and not widespread. A 40' container holds 20 pallets. The handling throughput can be:


15 cont./hour per crane,
or: 300 pallet/hour per crane,
or: 14,000 box/hour per crane
or: 280 ton/hour per crane
with 20 working hours/day: an average shipment can be loaded in less than one day.


iv) a fourth method exists, where boxes are loaded and unloaded in bulk. Special devices are used, based on conveyors: mobile ones, assembled for each call, or mounted on gantries (ref: Antwerp). Productivity vary between the first and second case and may be higher, depending on the level of equipment.


Appendix no. 2: waiting time and berth occupancy rate: table and graphs

Table E2/E2/N: CNUCED
Graphs: French Ministère de l'Equipement: Service Central Technique des Ports Maritimes et des Voies Navigables

1): Arrival at random, service time at random

2): Arrival at random, service time Erlang 3

3): Arrival at random, service time: constant


4): Arrival and service time : Erlang 2

Berth occupancy rate


No. of


Berths
Ratio:
Average
waiting time
Vs. Average
service time
%
1
2
3
4
5
6
7
8
10
0.02
15
0.03
0.01
20
0.06
0.01
25
0.09
0.02
0.01
30
0.13
0.02
0.01
35
0.17
0.03
0.02
0.01
40
0.24
0.06
0.02
0.01
45
0.30
0.09
0.04
0.02
0.01
0.01
50
0.39
0.12
0.05
0.03
0.01
0.01
0.01
55
0.49
0.16
0.07
0.04
0.02
0.02
0.02
0.01
60
0.63
0.22
0.11
0.06
0.04
0.03
0.02
0.01
65
0.80
0.30
0.16
0.09
0.06
0.05
0.03
0.02
70
1.04
0.41
0.23
0.14
0.10
0.07
0.05
0.04
75
1.38
0.58
0.32
0.21
0.14
0.11
0.08
0.07
80
1.87
0.83
0.46
0.33
0.23
0.19
0.14
0.12
85
2.80
1.30
0.75
0.55
0.39
0.34
0.26
0.22
90
4.36
2.00
1.20
0.92
0.65
0.57
0.44
0.40

›››File
FROM THE HOME PAGE
Sultan Ahmed bin Sulayem leaves DP World after Epstein's involvement
Dubai
It Kazim appointed president and Yuvraj Narayan managing director
Eurogate and APM Terminals will invest a billion euros for the development of the North Sea Terminal Bremerhaven
Bremen/The Hague
CK Hutchison threatens appeals against APM Terminals if it will assume the management of the Panamanian ports of Cristóbal and Balboa
Hong Kong
Tomorrow will be inaugurated the new container terminal of transhipment of Damietta
Bremen/Melzo
Its ability to annual traffic will rise up to 3,3 million teu
Fincantieri presents an industrial plan that foresees the doubling of the production capacity of military vessels in Italian shipyards
Milan
For civil production, a reallocation of volumes to Romanian shipyards and an expansion in Vietnam are planned.
Fincantieri and Generative Bionics sign agreement to develop humanoid welding robots.
Trieste/Genoa
The first tests at the Sestri Ponente shipyard are scheduled for the end of this year
Slight increase in annual freight traffic handled by Croatian ports
Zagreb
Sharp drop in dry bulk offset by increase in liquid cargoes and record containers
The Grendi group expects to close 2025 with a record turnover of 158 million euros (+33%)
Genoa
Revenues increased by 10%, net of the effect of the acquisition of Dario Perioli.
South Korean HMM's quarterly and annual performances were negative.
South Korean HMM's quarterly and annual performances were negative.
Seoul
In 2025 the container fleet transported 3.94 million TEUs (+3.2%)
Offer to acquire European express courier InPost
Amsterdam/Luxembourg
It was submitted by a consortium comprising Advent International (37%), FedEx (37%), A&R Investments (16%) and PPF Group (10%)
Transocean and Valaris sign merger agreement
Steinhausen/Hamilton
The new company will have a fleet of 73 offshore vessels, including 33 ultra-deepwater drillships
Hapag-Lloyd expects to close the 2025 financial year with a 61% decline in operating profit.
Hamburg
Record loads transported by the fleet, growing by +8%.
FS establishes a company specializing in transport and infrastructure consultancy
London
The new company is based in London
Maritime traffic in the Suez Canal fell by 3.4% last year.
Maritime traffic in the Suez Canal fell by 3.4% last year.
Cairo
Growth of +9.0% in the fourth quarter alone. In December, transits increased by +13.1%.
The simplification law, rather than making things easier, complicates the lives of ship captains and burdens them with additional operational and legal responsibilities.
Genoa
BYD and Automar reach agreement for vehicle traffic through the port of Gioia Tauro.
Schiedam
The goal is to serve the central-southern Italian market.
Maersk Group announces 15% ground-based job cuts
Maersk Group announces 15% ground-based job cuts
Copenhagen
The quarterly and annual financial results are impacted by the reduction in the value of maritime freight rates.
In 2025, container traffic in the ports of Genoa and Savona-Vado Ligure reached a historic record of almost three million TEUs
Genoa
Cruise passengers increased by 6.1%; ferry passengers decreased by 4.0%.
Busan Port has again set its all-time record for annual container throughput.
Busan
Last year the total was 24.88 million TEUs (+2.0%)
Panama Ports Company has initiated arbitration proceedings against the Republic of Panama
Panama
Extensive damage reported and state authorities' reluctance to respond to repeated requests for confrontation
In 2025, freight traffic in Sardinia's ports grew by +3.0%
Cagliari
Slight decline in cruise passengers contained by the launch of home ports in Cagliari and Olbia
Freight traffic in the port of Barcelona to remain stable in 2025
Barcelona
In the fourth quarter alone, 16.7 million tonnes were handled (+4.5%)
Maersk and Hapag-Lloyd bring back India/Middle East-Mediterranean service via Suez
In 2025, ships transiting the Panama Canal increased by +14.1%
In 2025, ships transiting the Panama Canal increased by +14.1%
Panama
The ports of the Central American nation handled 9,915,357 containers (+3.6%)
Last year, container traffic in the port of Tangier Med reached a record 11.1 million TEUs (+8.4%)
Last year, container traffic in the port of Tangier Med reached a record 11.1 million TEUs (+8.4%)
Anjra
New all-time high in total goods
In 2025, Turkish ports handled a record traffic of 553.3 million tonnes of cargo (+4.0%)
Ankara
Container traffic in Italy reached a new all-time high of 678,715 TEUs (+9.8%). Ship traffic through the Bosphorus Strait declined.
APM Terminals will take over the interim management of the Panamanian ports of Cristóbal and Balboa.
Panama
President Mulino urged Panama Ports Company to cooperate fully in view of this new phase
New crop of historic records harvested by Chinese ports
New crop of historic records harvested by Chinese ports
Beijing
In 2025, maritime ports handled 11.63 billion tons of goods (+3.7%)
PPC denounces the contradictory nature of the ruling by the Supreme Court of Justice of Panama with respect to the current legal framework
Balboa
The company does not exclude the possibility of resorting to national and international legal action
Lukoil signs agreement with US-based Carlyle to sell the Russian group's international assets
Fly
The transaction will need to be authorized by the U.S. Office of Foreign Assets Control.
Panama's Supreme Court of Justice declares the law on the concession contract with the Panama Ports Company unconstitutional.
Panama
Last year, PPC port terminals handled 3.9 million containers
Royal Caribbean Cruises has ordered two new cruise ships from Chantiers de l'Atlantique with options for four more
Royal Caribbean Cruises has ordered two new cruise ships from Chantiers de l'Atlantique with options for four more
Miami
New orders for ten new river vessels are planned. A record financial year.
CMA CGM establishes a joint venture with Stonepeak to which it will contribute ten container terminals
New York/Los Angeles
The American company will own 75% and 25% of the shares, respectively. It will invest 2.4 billion dollars.
German rail freight companies reject 37% increase in train path prices
Berlin
Die Güterbahnen urges the Minister of Transport to present the promised reform of the fare system
FS Logistix increases weekly rotations on the Duisburg-Milan railway line from six to ten
Milan
Two daily connections are made in each direction
In the fourth quarter of 2025, freight traffic in the port of Antwerp-Zeebrugge decreased by -4.9%.
Antwerp
For the whole year the decline was -4.1%
Valletta Cruise Port records record annual cruise traffic
London
In 2025, there were 963 thousand passengers (+2.3%)
Evergreen invests up to nearly $1.5 billion in the construction of 23 container ships
Taipei
Seven 5,900 TEU vessels have been ordered from Jiangsu New Yangzi Shipbuilding and 16 3,100 TEU vessels from CSSC Huangpu Wenchong Shipbuilding.
In 2025, Spanish ports handled a record container traffic of almost 19 million TEUs
Madrid
New historic highs also for conventional goods and passengers
First container transhipment operation in an Algerian port
First container transhipment operation in an Algerian port
Algiers
It happened on Sunday at the port of Djen Djen
Truckers from Serbia, Bosnia and Herzegovina, Montenegro, and North Macedonia block borders
Belgrade
Week-long protest against the EU's new entry/exit system
Resumption of attacks against ships in the Red Sea region threatened
Tehran
They would be implemented in response to an escalation of US and allied military actions in the region.
New annual record for maritime traffic in the Straits of Malacca and Singapore
New annual record for maritime traffic in the Straits of Malacca and Singapore
Port Klang
Last year, for the first time, over 100,000 ships passed through
New record of sailors abandoned by shipowners
London
In 2025, 6,223 crew members from 410 ships were abandoned
Two FMC commissioners call on the US government to take action against Canadian and Mexican ports
Washington
Enforcement of provision aimed at preventing freight carriers from evading the Harbor Maintenance Fee urged
Annual container traffic handled by the port of Algeciras remains stable.
Algeciras
A 6.2% decrease in the weight of goods in containers was recorded
The EU Commission authorizes Italy to provide financial support for rail operations in ports.
Rome
Incentives for a maximum total of 30 million euros over five years
Shipping companies urge further incentives to speed up restoration of Suez Canal transits
Shipping companies urge further incentives to speed up restoration of Suez Canal transits
Ismailia
The need to reduce insurance premiums for vessels transiting the Red Sea region was also highlighted.
€3.1 million in unpaid regional maritime property fees recovered in Campanian ports
Naples
422 default notices to non-compliant dealers
In November 2025, freight traffic in the ports of Genoa and Savona-Vado dropped by -5.5%.
Genoa
The two airports recorded percentage variations of -7.5% and +0.6% respectively
EU ETS: Interferry calls for a halt to the 100% charge for ferry emissions in 2026.
Victoria
The vast majority of the revenues from the maritime ETS - the association denounces - are diverted to the national budgets of the Member States.
The new configuration of the Ocean Alliance service network confirms seven calls at Italian ports
Hong Kong/Taipei
Two at the port of Genoa, two at that of La Spezia and one stop each at the ports of Vado Ligure, Trieste and Salerno
Last year, freight traffic in the port of Marseille-Fos increased by +5%
Last year, freight traffic in the port of Marseille-Fos increased by +5%
Marseille
Cruise passengers grow by +7%
AD Ports has acquired the Spanish shipyard Astilleros Balenciaga.
Abu Dhabi
Transaction worth 11.2 million euros
CMA CGM reports three services on the route around the Cape of Good Hope
Marseille
The international scenario - explains the French company - is complex and uncertain
COSCO Shipping Ports' terminals handled record container traffic last year
Hong Kong
Growth of +6.2% over 2024
In the fourth quarter of 2025, freight traffic in the port of Venice grew by +13.5%
Venice
An increase of +4.9% was recorded for the whole year
Buffer areas to decongest the North West logistics system
Genoa
The proposal is from Connect. Let's remember, Palenzona warns, that the Italian system depends on road haulage.
In 2025, Russian ports handled 884.5 million tons of cargo (-0.4%)
In 2025, Russian ports handled 884.5 million tons of cargo (-0.4%)
St. Petersburg
In the fourth quarter alone, traffic was 231.1 million tonnes (+6%)
The port of Civitavecchia has set a new annual cruise traffic record
Civitavecchia
A 5.4% increase in transit passengers. Disembarking and embarking passengers remained stable.
A ship coming from Russia was seized in the port of Brindisi
Toasts
Alleged violation of sanctions against the Russian Federation
FS Logistix takes over railway operations in Area 6A of the Port of Antwerp.
Antwerp
New generation hybrid locomotives will be used
Greek Shipowners' Association urges EU to take measures to protect ships and crews
Piraeus
Call for expressions of interest for the refurbishment and management of the cruise terminal at the Port of Gibraltar
Gibraltar
Applicants must be willing to fully finance the work
In 2025, acts of piracy against ships increased by +18%
In 2025, acts of piracy against ships increased by +18%
Kuala Lumpur
A 43% decrease in accidents was recorded in the last quarter
InRail to manage the Interporto Pordenone intermodal terminal for a year
Pordenone
Temporary solution in view of the establishment of a public-private company
Turkey's Kuzey Star Shipyard to Build Shipyard in Syria's Tartous Port
Damascus
An investment of at least $190 million over five years is expected
In 2025, cargo traffic in Ukrainian ports decreased by -15%
Kiev
Container traffic grows by 66%
Container traffic in the port of Hong Kong decreased by 5.7% last year.
Hong Kong
In the fourth quarter alone the decline was -8.0%
In 2025, PSA's port terminals handled record container traffic
Singapore
New peaks in volumes handled in Singapore and the group's overseas terminals
Chinese CMPort's port terminals handled record container traffic last year
Hong Kong
The total was 151.5 million TEUs, an increase of +4.0% over 2024.
COSCO orders 12 new 18,000-TEU and six 3,000-TEU containerships
Hong Kong
Jiangnan Shipyard, China Shipbuilding Trading, and COSCO Shipping Heavy Industry win $2.7 billion in orders.
The port of Trieste closed 2025 with a 0.7% growth in freight traffic thanks to the increase in crude oil prices.
Trieste
The port of Gioia Tauro has once again set its container traffic record
The port of Gioia Tauro has once again set its container traffic record
Gioia Tauro
In 2025, the previous peak recorded the previous year will increase by +14%.
Port of Singapore sets new all-time container throughput record
Port of Singapore sets new all-time container throughput record
Singapore
The port confirms its position as the world's second largest container port
Meyer Turku completed the design of a cruise ship to zero net emissions
Turku
The main fuel is biomethanol
Last year the turnover of Kalmar grew by +1%
Helsinki
Operating income, net profit and new orders in increase respective of +26%, +28% and +8%
Terminal Investment Limited puts hands on the Peruvian port of Pisco
Lima
Acquired the Portuario de Paracas Terminal
Assagenti urges a more constant and timely information on the progress of the work of the new dam of Genoa
Grimaldi has taken delivery of the Grande Michigan
Naples
It is the eighth Pure Car and Truck Carrier ammonia ready of the Neapolitan group
Meeting between the presidents of the Maritime Federation and Assoporti
Rome
Mario Mattioli and Roberto Petri addressed the main issues of the maritime cluster
Morocco's Marsa Maroc participates in the development of the port of Monrovia
Casablanca
Contract for the management of two docks and the construction of a multipurpose terminal
South Korea's Pan Ocean buys ten VLCCs from compatriot SK Shipping
Seoul
Transaction valued at approximately $668 million
Roberto Mantovanelli has been appointed Secretary General of the Northern Adriatic Port Authority.
Venice
The 2026-2028 Three-Year Operational Plan for the Ports of Venice and Chioggia has been approved.
Stefano Messina has been confirmed as president of Assarmatori
Rome
He will also lead the shipowners' association in the four-year period 2026-2030
In 2025, Albanian ports handled a record traffic of 8.2 million tons of goods (+6.2%)
Tirana
A new peak in passengers also amounted to 1.7 million units (+6.4%)
WASS (Fincantieri) has been awarded a contract by Saudi Arabia for the supply of lightweight torpedoes
Trieste
The order is worth more than 200 million euros
Oxin (Somec) awarded a major order for the construction of kitchen, pantry, catering and bar areas for two cruise ships
San Vendemiano
The value of the order is 53 million euros
Sogedim launches a daily service between Carpi and Campogalliano/England
Carpi
Daily shuttle departing from the logistics hubs of Campogalliano, Carpi and Prato
Danaos Corporation reports record quarterly and annual revenue.
Athens
Profits are falling
CPPIB and OMERS are considering selling their 67% stake in Associated British Ports.
London
Maersk orders eight 18,600 TEU dual-fuel containerships
Copenhagen
Built by New Times Shipbuilding Co., they will be delivered between 2029 and 2030.
PaxOcean opens new shipyard in Singapore
Singapore
It occupies an area of 17.3 hectares
The largest container ship ever arrived in the port of Trieste
Trieste
Port of call of the "MSC Diana" which has a capacity of approximately 19,000 TEUs
Antin Infrastructure Partners acquires U.S. shipbuilder Vigor Marine Group
New York
It has shipyards in Seattle, Portland, Vancouver, San Diego and Norfolk
In 2025, Moroccan ports handled a record traffic of 262.6 million tons of goods (+8.9%)
Rabat
Transhipment equal to 50.5% of the total
Yang Ming deploys first of five 15,500 TEU dual-fuel LNG vessels on Asia-Mediterranean route
Keelung
It will be used in the MD2 service
Study highlights challenges for LNG containerships in complying with future cold ironing connection requirements
Berlin/Hamburg
Fincantieri and Wsense reach agreement to offer cutting-edge underwater systems
Trieste
Co-development of advanced wireless technology solutions planned
Study finds high levels of persistent organic pollutants caused by shipbreaking activities
Brussels
Port of Livorno: tender for ship-generated waste management begins
Livorno
The expected value of the contract is over 40 million euros
DSV revenue and profits impacted by Schenker acquisition
Copenhagen
In 2025, turnover grew by +48.0%
Wärtsilä reports significant growth in quarterly and annual results for the Marine segment
Helsinki
The Finnish group's new orders acquired in 2025 remain stable.
Dutch company Portwise has been bought by its compatriot Haskoning
Rijswijk
The company offers solutions for optimizing terminal operations through automation and electrification
Construction of the first of six container ships for Italia Marittima has begun in China.
Trieste
The ships, which will be able to use traditional fuel and methanol, will have a capacity of 2,400 TEUs
In the Strait of Hormuz, armed vessels ordered a US tanker to stop
Southampton/London
GTS announces new rail services between the port of Genoa and central and southern Italy.
Bari
Connections via the Segrate Milan terminal
The number of dual-fuel vessels employed by liner shipping lines is set to double by 2025
Washington
Currently, 74% of the order book consists of units of this type
Kuehne+Nagel expands CargoCity South at Frankfurt Airport
Schindellegi
A new facility will be completed and taken over at the end of 2028
AD Ports signs agreement to build and operate multipurpose terminal at Matadi Port
Abu Dhabi/Kinshasa
Relaunch of the Banana Deepwater Port Construction Project
Confitarma: The Revenue Agency's position risks having serious repercussions on Italian seafarers' employment.
Rome
Bucchioni appointed pro tempore president of the Association of Freight Forwarders of the Port of La Spezia
La Spezia
The tender for the development of the shipbuilding hub in the port of Ancona has begun.
Ancona
The AdSP Management Committee has approved the call for tenders
ONE's quarterly financial performance declines further
Singapore
The volume of containerized cargo transported by the fleet remains stable
Laura DiBella's nomination for FMC presidency has been signed.
Washington
His term will expire on June 30, 2028.
Port of Singapore saw record bunker deliveries in 2025
Singapore
PSA-MOL joint venture to manage a new ro-ro terminal
The port of Taranto was visited by a delegation from the Japanese FLOWRA
Taranto
The association brings together 21 of the main Japanese energy players
ABB's new orders in a quarter exceed $10 billion for the first time.
Zurich
Growing demand in the maritime, port and railway sectors
In the United States, MSC was fined a total of $22.67 million
Washington
The Federal Maritime Commission has released the results of an investigation
CSC Vespucci and Livorno Reefer will form a single platform dedicated to fruit and vegetable and exotic products in the port of Livorno
Signal Ocean has acquired AXSMarine
Paris/London
The company offers web platforms to support the ship charter sector
Stena RoRo has placed an order for two ro-ro vessels in China with options for four more.
Gothenburg
They were designed in cooperation with the Italian Naos
Shanghai Zhonggu Logistics Co. to Order Four New 6,000-TEU Containerships
Shanghai
The order will include options for two additional vessels
UPS revenues decreased by 2.6% in 2025
In the last quarter alone, a decrease of -3.2% was recorded
ICS has published its periodic analysis of flag state performance
London
Michail Stahlhut will step down as CEO of Hupac in May
Noise
Bertschi: Under his leadership, the company's position as a leading provider of combined road/rail transport in Europe has been strengthened.
Members of the Ravenna Marine Resource Partnership Body have been appointed.
Ravenna
It will meet for the first time on February 4th and will remain in office for four years
Messina (Assarmatori): MIT's decree on cold ironing is a good thing.
Rome
This is a fundamental step - he underlined - to ensure that the electrification of the platforms is actually usable.
Contship has joined the Digital Container Shipping Association's DCSA+ program.
Melzo
Among the goals, improving the efficiency of terminal operations, the accuracy of planning and collaboration with shipping companies.
The Argentine Port Workers' Federation threatens a strike at national ports.
The Silver
Action in support of workers at the port of Concepción del Uruguay
In 2025, freight traffic in the port of Taranto grew by +0.8%
Taranto
In the last quarter alone, a decrease of -22.6% was recorded
Last year, container traffic in the port of Valencia grew by +3.4%
Valencia
5,662,661 TEUs were handled
Fincantieri wins Italian Navy contract to enhance naval vessels' cyber resilience
New facility in Charleston for the production and testing of marine power and propulsion systems
Arlington
It was inaugurated by Leonardo DRS, a subsidiary of the Italian Leonardo
Project to strengthen maritime and port cybersecurity
Brest/Brussels/Rome
The partners are France Cyber Maritime, FEPORT and the Federation of the Sea
SAILING LIST
Visual Sailing List
Departure ports
Arrival ports by:
- alphabetical order
- country
- geographical areas
Container traffic at the Port of Los Angeles fell by 10.6% in the last quarter of 2025.
Los Angeles
A decrease of -0.6% was recorded for the whole year
In the first six months of operation InnoWay Trieste produced 170 railway wagons
Trieste
The construction of 600 units is planned in Bagnoli della Rosandra in 2026
Ferretti rejects KKCG Maritime's partial and conditional voluntary takeover bid.
Milan
Strong confidence in the company's long-term strategy reaffirmed
Haropa Port sets new container traffic record
Le Havre
Last year, overall freight traffic increased by +2%
Decio Lucano, the dean of shipping journalists, has passed away.
Genoa
His paper adventures are countless, including "Vita e Mare" and "TMM", but also digital with "DL News"
Marsa Maroc orders 106 electric terminal tractors from Terberg
Benschop
They will be employed in the port of Nador West Med
Contargo acquires 50% of Cargo-Center-Graz Logistik
Mannheim
The German company extends its intermodal network to the Adriatic ports of Koper and Rijeka.
A single binding offer from Dubai for the purchase of the Venice Ro-Port Mos
Venice
The company manages the terminal for the motorways of the sea and cruises in Fusina
The Port of Long Beach handled record container traffic in 2025
Long Beach
In the last quarter, a decrease of -8.8% was recorded
HMM to introduce AI-based autonomous navigation solutions on 40 vessels
Seoul
Contract with Avikus and agreement with KSOE
Two new rail connections to Germany from the Padua Interport
Padua
They are operated by InRail and LTE Italia
Intersea has become the general agent in Italy for the Portuguese GS Lines
Genoa
The shipping company is part of Grupo Sousa
MSC and Qatari company Maha to develop and manage the Libyan port of Misurata
Paris/Misurata
An investment of 1.5 billion dollars is expected
F2i has been awarded the concession for the Lavagna tourist port
Milan
The concession contract will have a duration of 50 years
Eni launches the hull of the Coral North FLNG
Geoje/San Donato Milanese
It will be used offshore Cabo Delgado, north of Mozambique.
Laghezza has acquired a logistics warehouse in Sarzana
La Spezia
The aim is to establish a local hub for local production activities.
The Red Sea Container Terminal at the Egyptian port of Sokhna has been inaugurated.
Sokhna
It is operated by a joint venture of Hutchison Ports, COSCO and CMA Terminals
The GNV Altair ferry has joined the GNV fleet
Genoa
It has a capacity of 2,700 passengers and 915 linear metres of rolling stock.
Maersk confirms resumption of MECL transits through the Suez Canal
Copenhagen
The line connects India and the Middle East with the US East Coast
Ignazio Messina & C. has acquired full control of Thermocar
Genoa
The Genoese company operates in the temperature-controlled refrigerated container logistics sector.
Genco's board of directors rejected Diana Shipping's acquisition proposal.
New York/Athens
The American company, however, leaves a glimmer of hope by admitting the validity of the merger
MSC will include the port of Trieste in the Dragon Italy-USA service
Geneva
The Julian port will be reached starting from the second half of February
De Wave Group has acquired French company DL Services.
Genoa
The company specializes in the design of industrial kitchens and the supply of technical components and spare parts on board
CMA CGM's TUX transatlantic service will call at the port of Salerno
Marseille
The line connects Turkey with the East Coast of the USA
Cruise traffic in the port of Piraeus increased by +9% last year
Piraeus
Approximately 1.85 million passengers moved
New intermodal connections between Northern Italy and Belgium by GTS Rail and CargoBeamer
Bari/Leipzig
Activated on the Padua-Zeebrugge and Liège-Domodossola lines
In 2025, cruise traffic in the port of Genoa grew by +6.5%
Genoa
Ferry passengers down 3.6%
Grimaldi took delivery of the PCTC Grande Manila
Naples
The vessel has a total capacity of 9,241 CEUs.
Expedition cruise ship Exploris One to be auctioned off
Nantes
It has a capacity of 144 passengers and 102 crew members.
SeaCube Container Leasing has acquired Martin Container.
Montvale
The company specializes in the refrigerated container segment
Pisano: The Simplified Logistics Zone has great strategic importance for the port of La Spezia.
La Spezia
RINA and HPC launch project to promote green ports in the Caspian region
Genoa
Five-year contract with the OSCE
Vard to build four Multi-Purpose Robotic Vessels for Ocean Infinity
Trieste
The contract has a total value of over 200 million euros
Hanseatic Global Terminals will become sole owner of Florida International Terminal
Rotterdam
A conference on congestion in the North West logistics system will be held in Genoa on January 19th.
Genoa
It will be held at the Transparency Hall of the Liguria Region
The transportation sector enters a turning point with the adoption of artificial intelligence
Ulm
However, most companies are still in the early stages of this process.
Work completed to widen the access channel to the port of Livorno.
Livorno
The width between the two banks will be increased from 70 to 120 meters
Nexans sets a record for the depth of laying a high-voltage submarine cable on the Tyrrhenian Link
Paris
Installation at -2,150 meters
Funds for Spanish ports to adapt to the use of wind energy and other marine renewable energy sources
Madrid
Program with a total value of 212 million euros
CMD - Costruzioni Motori Diesel returns to wholly Italian ownership
Atella
Giorgio and Mariano Negri have acquired 67% of the capital held by the Chinese Loncin Motor Co.
Intesa Sanpaolo is financing the construction of three PCTCs for Grimaldi Euromed.
Milan
The new ships will be delivered later this year
Medlog acquires Australian intermodal operations of Seaway
Fremantle
The transaction will be completed within the first quarter of this year.
MIT has updated cybersecurity measures for national ships, ports and port facilities
Rome
A circular has been published which, among other things, introduces staff training
V.Group has bought the Danish company Njord
London
The company offers the shipping industry solutions for energy efficiency and decarbonisation
PORTS
Italian Ports:
Ancona Genoa Ravenna
Augusta Gioia Tauro Salerno
Bari La Spezia Savona
Brindisi Leghorn Taranto
Cagliari Naples Trapani
Carrara Palermo Trieste
Civitavecchia Piombino Venice
Italian Interports: list World Ports: map
DATABASE
ShipownersShipbuilding and Shiprepairing Yards
ForwardersShip Suppliers
Shipping AgentsTruckers
MEETINGS
A conference on congestion in the North West logistics system will be held in Genoa on January 19th.
Genoa
It will be held at the Transparency Hall of the Liguria Region
Spediporto's conference "Take opportunities navigating trade tensions" will be held in Genoa on December 1st and 2nd.
Genoa
It will be held at the Conference Hall of Banca Bper
››› Meetings File
PRESS REVIEW
Auction of megaterminal in Santos may be postponed due to deadlock within the Federal Government
(A Tribuna)
East Port Said Port faces a new challenge with Europe's carbon rules for shipping
(EnterpriseAM)
››› Press Review File
FORUM of Shipping
and Logistics
Intervento del presidente Tomaso Cognolato
Roma, 19 giugno 2025
››› File
Fire aboard the Majestic ferry in the Port of Genoa
Genoa
The flames were extinguished by the intervention of the on-board fire brigade and did not cause any injuries.
COSCO to acquire control of German logistics company Zippel
Hamburg
Agreement to acquire 80% of its capital
Colombo Port Sets New Annual Container Traffic Record
Columbus
Sri Lanka Ports Authority signs agreement with French shipping group CMA CGM
Viasat to exit British company Navarino's capital
London
ICG to support the Tsikopoulos brothers in reinvesting in the company
The Palau government ensures the full operation of the Naval Registry
Koror
Moses (BMT): Services continue to be provided in accordance with international procedures and standards
In the first nine months of 2025, freight transported on the Austrian rail network increased by +1.4%
Vienna
Growth of +4.9% was recorded in the third quarter alone
Saipem wins $425 million offshore contract to develop the Sakarya gas field.
The decree for the distribution of PNRR resources to interports has been signed.
Rome
The disbursement of 1.9 million euros is expected
Messina, a Genoese company, launches a new service to Algeria.
Genoa
The rotation touches the ports of Fos, Genoa, Barcelona, Algiers, Fos
FS Logistix is the first company in Europe to certify its carbon footprint for freight transport.
Rome
The FS group company has obtained ISO 14067 certification
WASS (Fincantieri Group) wins torpedo supply contract for Indian Navy
Trieste
Contract with a total value of over 200 million euros
FHP Intermodal will become operational on January 1st
Milan
FHP Group completes the integration process between its subsidiaries CFI Intermodal and Lotras
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio
No part may be reproduced without the express permission of the publisher
Search on inforMARE Presentation
Feed RSS Advertising spaces

inforMARE in Pdf
Mobile