Today the Indian government approved the project for the
construction of a second container terminal in the port of
Kamarajar (Ennore) within a public-private partnership
which foresees an investment of about 42.9 billion rupiah (462
million dollars) to build a 900-meter quay
with a depth of -18 meters that will have a
annual traffic capacity of 2.0 million TEU.
The project will be carried out in two phases, with the first
which will involve an investment of 24.3 billion rupees and the
second of 18.6 billion. The first phase will have a capacity
of 1.1 million TEU and the second of 900,000 TEU. Furthermore, they are
additional costs of 4.5 billion rupees are expected for
the execution of dredging by Kamarajar Port Limited
(KPL), the company that manages the port and which is
wholly controlled by the Chennai Port Authority. The new
terminal will be able to accommodate the largest container ships
currently in service.
The project will be implemented according to the model
Design-Build-Finance-Operate-Transfer and the concession will have
a duration of 40 years, including construction activities
performed in 48 meters, of which 24 months were for the first phase alone.
Last August, KPL began the submission phase
of the offers for the implementation of the project, with a fixed deadline
to last October 30, which was then postponed to
next December 15.